View Single Post
Old 17-01-2020, 21:07   #2096
Hugh
laeva recumbens anguis
Cable Forum Team
 
Hugh's Avatar
 
Join Date: Jun 2006
Age: 67
Services: Premiere Collection
Posts: 42,102
Hugh has a golden auraHugh has a golden aura
Hugh has a golden auraHugh has a golden auraHugh has a golden auraHugh has a golden auraHugh has a golden auraHugh has a golden auraHugh has a golden auraHugh has a golden auraHugh has a golden auraHugh has a golden auraHugh has a golden auraHugh has a golden auraHugh has a golden aura
Re: Brexit Development(s) Discussion

Quote:
Originally Posted by Pierre View Post
Apparently the “Brexit Bong” incurs a heavy uplift.......

https://www.telegraph.co.uk/politics...imes-sounding/
Basic Project/Change Management - you want a change to plan, and you have six to twelve months to arrange the work, the work plan can be amended so the work is done at normal costing levels - you want it done in a compressed timescale with very little notice, it will cost a lot more; not just the cost of getting the work done at an elevated rate, because of the short time scale, but also the cost of all the work and resources you had planned in that time (and the time and resources it takes to get back on to the original plan).

Quote:
A spokesman for the House of Commons said: "The striking of Big Ben on these occasions was coordinated around the planned works so as to minimise the impact on the project costs and to ensure it did not result in any delay.

"If the project team are required to strike the bell with less notice, the costs would substantially increase due to the unexpected impact on the project schedule.

"The cost of striking the bell for New Year’s Eve and Remembrance Sunday has been factored in to the planned programme well in advance, to ensure that testing and striking have no impact on planned works, therefore causing no delay and minimum cost.

“The estimated cost is £120,000 to sound the bell, plus circa £100,000 for each week of delays.

"This estimate is based on the fixed cost of installing, testing, operating and dismantling the temporary mechanism used to sound the bell during the works, plus an allowance for each week that work on the project is delayed.

"As such, the minimum cost of sounding Big Ben would be £320,000 but could be up to £500,000.”
__________________
There is always light.
If only we’re brave enough to see it.
If only we’re brave enough to be it
.
If my post is in bold and this colour, it's a Moderator Request.

Last edited by Hugh; 17-01-2020 at 21:13.
Hugh is offline