Pierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny starsPierre has a pair of shiny stars
Re: Expand the cable network

£10,000 a meter is a bit too high

On avg (as differnent contractors have different rates around the country)

eg For fibre optic.

to excavate a 4way duct in the f/w = £37 per m
the tee to each property £ 22 per no.
To backfill the trench = £13 per m2
to tarmac the trench = £27 per m

to pull in a large fibre optic = £0.65 per m
Large fibre optic cable costs = £4.50 per m
to joint a large fibre optic cost = £2000 per joint
To build and activate a cab = up to £1100 (depending of size of cab)
F/w chambers up to £900 depending on size of chamber