Grenfell cladding was changed to cheaper version, reports say
Documents seen by BBC show contractors were asked to fit aluminium instead of more fire-resistant zinc, saving £300,000
Cladding proposed for Grenfell Tower during a multimillion-pound refurbishment was changed to a cheaper, less fire-resistant version to make a saving of less than 4% of the final cost of the project, according to reports.
Documents seen by the BBC show contractors working for Kensington and Chelsea council were asked in 2014 to use aluminium cladding instead of zinc, to save £300,000. The wider refurbishment cost £8.6m
The leaders of Kensington and Chelsea council have been accused of shameful behaviour after shutting down the first cabinet meeting since the disaster after attempts to block the media from the hearing failed.